Listed below are the anticipated milestone dates for activity at Hartfields. Please note that these are aimed at providing a guide only and are subject to possible changes.


31 July 2008
Inaugural ceremony to mark the official opening of Hartfields.

18 August 2008

First residents move in (Phase 1A)
On-site communal facilities open.


October 2008

Phase 1B (64 units of accommodation), ready for move-in.


December 2008

Phase 2 (52 units of accommodation), ready for move-in.


March 2009

Phase 3 (43 units of accommodation), which is the final phase, ready for move-in.